The municipality of Port Hope has released a year’s worth of construction details for the Walton Street redevelopment project.
Beginning April 22, traffic control detours and closure will be setup around the work zone perimeter.
Additional details for the project include:
• Early May:
— Removals
— Temporary water installation
• May to August
— Storm, Sanitary and Watermain underground work
• Canada Day
— partial opening of Queen Street for one-way traffic
• July
— Electrical Work
• September
— Traffic Signal work
• October
— Curb and Sidewalk concrete work and Base Asphalt
GoNorthumberland.ca will keep you up-to-date as the redevelopment continues.
(Written by: Noah Lorusso)